For over a decade, MKR evaporators have been treating slurry and digestate on residue and food waste plants across Europe. A selection of reference projects, with the evaporator used, the plant input and the achieved volume reduction.

* All data refers to results achieved under specific operational conditions. Actual efficiency may vary based on substrate composition and local plant setup. We recommend a laboratory evaluation of your sample before investment.

What are the use cases for MKR's evaporators?

MKR evaporators treat slurry and digestate across very different inputs, from food-waste and slaughter-waste plants to partial-stream zero-liquid digestate and the liquid from washing digestate fibres for peat-substitute production.

Reference 01: DV-Evaporator on a food-waste AD plant, Switzerland

A 4-stage DV evaporator has been treating digestate from food waste and food-industry residues with CHP waste heat since 2020.

​

  • Machine: 1 × DV-Evaporator, 4-stage, with vapour scrubber for ASL

  • Plant input: food waste and food-industry residues plus rumen contents from the slaughterhouse, approx. 30,000 t/a

  • Heat source: CHP waste heat

  • Distillate: reused as process water in the plant's depackaging line

  • Concentrate and ASL: taken over by a service provider as raw material for fertiliser production

  • Measured on 51 complete days (26 Jun to 3 Oct 2026): 82 % of the time evaporating, on average approx. 31 m³ distillate per day; at full load approx. 40 m³ per day at approx. 350 kW, 4.5 to 4.7 l distillate per kWh heat

  • Background: the evaporator replaced a reverse osmosis unit that did not work on this digestate

  • In operation since: 2020

  • See the measured data: Operating data and evidence

​

Reference visits and talks with the plant operator are possible.

Visitor group with Michael Köhnlechner at the MKR DV-Evaporator on a food-waste AD plant in Switzerland
Operating data of a 4-stage DV-Evaporator on food-waste digestate in Switzerland: distillate per day as weekly average and share of time per operating state, 51 complete days, 26 June to 3 October 2026

Reference 02: Two DV lines on a food-waste AD plant, Western Germany

Two 3-stage DV lines have been treating digestate from food waste, restaurant waste, flotation sludge and grease trap contents with CHP heat since 2019. They reduce the volume that has to be stored and spread by around two thirds.

​

  • Machine: 2 × DV line, each 3-stage, with vapour scrubber for ASL

  • Plant input: food waste, restaurant waste, flotation sludge and grease trap contents

  • Heat source: CHP heat

  • Measured (remote monitoring 07/2023 to 08/2025): around 40 m³ of distillate per line on a full operating day, around 80 m³ with both lines; around 3 m³ of digestate becomes around 1 m³ of concentrate

  • In operation since: line 1 in April 2019, line 2 in 2020

  • See the measured data: Operating data and evidence

​

Reference visits and talks with the plant operator are possible.

Heatmap of the evaporating share of Reference Plant Western Germany by weekday and hour in the 2023/24 season, staffed hours Monday to Friday 06:00 to 22:00 marked.

Reference 03: MVR15 for washing liquid from digestate fibres (peat substitute), Germany

An electric MVR15 evaporates the liquid used to wash separated digestate fibres before they are made into peat substitute. The distillate goes back to the washing loop and the concentrate keeps the nutrients and solids, so the loop is closed.

  • Machine: 1 × MVR15 (mechanical vapour recompression, electric)

  • Medium: washing liquid from screw-press digestate fibres (fines and salts washed out), not digestate

  • Energy: approx. 40 kWh electricity per m³ distillate (approx. 25 l/kWh) on this washing liquid; for digestate we state 22.5 l/kWh

  • Process: screw press separates the fibres; fibres are washed and conditioned into peat substitute; the washing liquid is evaporated in the MVR; distillate returns to the washing loop

  • Background: the MVR replaced an ultrafiltration and reverse osmosis concept that did not work on this medium, and shortened the process chain

Reference visits and talks with the plant operator are possible.

Proof of concept: before ordering, the operator tested the washing liquid in our laboratory, in our technical centre and on site with the MKR test unit

MKR MVR15 electric evaporator for washing liquid from digestate fibres, installed in the hall at the operating site in Germany

Reference 04: DV1000 for partial-stream zero liquid discharge, Germany

On an agricultural biogas plant fed mainly with slurry and farmyard manure, a 3-stage DV1000 evaporates the separated liquid phase. ASL is recovered as mineral fertiliser and the concentrate is dried together with the solids, so no liquid is left from this partial stream.

  • Machine: 1 × DV1000, 3-stage

  • Plant input: mainly slurry and farmyard manure

  • Process: separation, evaporation of the liquid phase, ASL recovery, concentrate dried with the solids

  • Heat demand: approx. 180 kW

  • Distillate per kWh heat: approx. 3.4 to 3.7 l

  • Volume reduction: approx. 5,000 m³ per year

  • In operation since: early 2021

Reference visits and talks with plant operators are possible at food-waste plants in Switzerland and western Germany and at the MVR plant in Germany.

MKR DV1000 evaporator at an agricultural biogas plant with partial-stream zero liquid discharge (ZLD) digestate treatment in Germany

Frequently asked questions